Ningbo Shulai Pump Gate Station | High-Capacity Integrated Pump Gate Retrofit Solution – Kaiquan

Discover how Shanghai Kaiquan upgraded the Ningbo Shulai Pump Gate Station with an integrated pump gate solution, increasing flood drainage capacity by approximately 50% without additional land or major reconstruction.

The Shulai Pump Gate Station is a key flood-control facility in Ningbo, Zhejiang Province, protecting surrounding urban areas during heavy rainfall and typhoon seasons. Originally equipped with 3 pumping units and a three-gate structure, the station had a total drainage capacity of 20 m³/s, which could no longer fully meet the region's growing flood-control requirements.

Kaiquan developed a customized retrofit solution, integrating 6 pump gate units into the existing structure and increasing drainage capacity by 10.8 m³/s. Before implementation, the engineering team conducted detailed site surveys and dimensional verification, followed by CFD hydraulic analysis and CAE structural analysis to optimize inlet flow conditions and ensure structural safety.

Key Technical & Operational Features

Higher Capacity Without Additional Land

By utilizing the existing three-gate structure, Kaiquan increased drainage capacity by approximately 50% without requiring additional project land or extensive civil reconstruction.

CFD & CAE Optimized Retrofit

CFD analysis optimized pump inlet flow conditions, while CAE analysis verified gate strength and stiffness, ensuring efficient hydraulic performance and structural reliability.

Cost-Effective Infrastructure Reuse

The solution retained the existing gate slots and hydraulic hoists following load verification. Maintenance of the original hydraulic power system further reduced modification costs while ensuring reliable gate operation.

Impact & Industry Recognition

Completed in just two months and accepted in August 2023, the project received a Ningbo Municipal Quality Engineering Award in 2024.

During Typhoon Co-May in July 2025, the upgraded station maintained the river water level below 0.7 m, with upstream levels stabilized between 0.4 and 0.5 m, demonstrating its flood-control performance under severe weather conditions.

The project highlights Kaiquan's capability to deliver high-performance, cost-effective pumping station retrofit solutions, combining advanced engineering analysis with existing infrastructure to enhance urban flood resilience.